This is a complete process definition document (PDD) for inbound receiving and put-away, also called goods receipt, warehouse inbound process or dock-to-stock. It describes how pallet deliveries are checked in at the gate, unloaded, counted against the advance shipping notice, inspected, labelled and stored, until the stock is available to the client in the warehouse management system. The company is fictional, but the roles, systems and exceptions are typical of a pallet warehouse.

Use it as a starting point. Replace the company details, keep the sections, and walk the floor with the gate clerks, operators and supervisors, because the real process is often different from the one on paper. Most warehouses change the discrepancy tolerance, the counting rule per client and the way advance notices arrive. Cross-docking, returns, cold storage and customs are left out on purpose.

1. Purpose and scope

This procedure describes how Lusolog Armazéns S.A. receives pallet deliveries and puts them away, from the moment a client announces a shipment or a truck arrives at the gate to the moment the pallets are in a storage location and the stock is confirmed available to the client. It gives the gate, the receiving team, supervisors, quality, forklift drivers and account managers one shared description of who does what, so that every pallet is counted, traceable and stored quickly, and so that damage and differences are documented before the carrier leaves.

In scope

  • Pallet deliveries for retail, cosmetics and household clients
  • Advance shipping notices received by EDI or email
  • Gate registration, dock door assignment and unloading
  • Counting, labelling and damage checks
  • Discrepancy handling with the client
  • Put-away to storage locations and stock confirmation

Out of scope

  • Cross-docking
  • Returns processing
  • Cold storage
  • Customs clearance

2. Process at a glance

Trigger
A client sends an advance shipping notice (ASN), or a truck arrives at the gate.
Starts when
The client sends the ASN, usually one day before arrival.
Ends when
The pallets are put away and the WMS shows the stock as available in the client portal.
Volume
About 46,000 inbound deliveries a year, roughly 180 per working day
Working hours
Two shifts, 06:00 to 22:00, Monday to Saturday.
Company in this example
Lusolog Armazéns S.A., a third-party logistics provider with a distribution centre in Azambuja, Portugal (about 210 employees)
Inputs
Advance shipping notice (EDI or email), CMR transport document, Pallets and cartons, Client counting rule, Client instructions on discrepancies
Outputs
Receipt in the WMS, Discrepancy report where needed, Pallet labels with batch and expiry date, Pallets in storage locations, Signed CMR returned to the carrier, Stock visible in the client portal

3. Roles and responsibilities

Client (external)
Sends the advance shipping notice, answers discrepancy reports and decides whether to accept unannounced deliveries.
Carrier (external)
Delivers the goods and hands over the CMR transport document at the gate.
Gate Clerk
Registers arriving trucks, matches them to the ASN, assigns dock doors, retypes email ASNs and closes the yard entry.
Receiving Operator
Opens and checks the truck, unloads, scans and counts pallets, flags discrepancies, and prints and applies labels using a handheld scanner.
Receiving Supervisor
Reviews discrepancies, decides how to receive, orders recounts, approves receipts with differences and reassigns blocked locations.
Quality Inspector
Inspects damaged or sampled pallets and records accept, quarantine or reject in the WMS.
Forklift Driver
Takes pallets from the receiving area to the assigned locations and confirms each placement by scanning.
Client Account Manager
Talks to the client about unannounced deliveries and discrepancies, and collects instructions.
Manhattan WMS (system)
Proposes a storage location for each pallet automatically and updates stock when the pallet is placed.

4. Systems

  • Manhattan WMS: receiving, locations and stock
  • Client ASN via EDI or email attachment
  • Handheld RF scanners and label printers
  • Yard booking spreadsheet in Excel
  • Client portal for stock visibility

5. Process map

Process diagram goes here

Draw your own swimlane: one lane per role from section 3, the steps from section 6 in order, and a diamond for each decision in section 7. Your process will differ from this example, so map it from what your team actually does.

6. Procedure, step by step

#StepWhoWhat happensSystemOutput
1Send the ASNClientSends the advance shipping notice by EDI or email, usually one day before arrival.EDI, emailASN received
2Enter an email ASNGate ClerkIf the ASN arrives by email, retypes it into the WMS as an expected receipt. About 35% of ASNs arrive this way, and each takes 10 to 15 minutes.Manhattan WMSExpected receipt in the WMS
3Arrive and hand over the CMRCarrierThe carrier arrives and the driver gives the CMR transport document to the Gate Clerk.Paper CMRCMR at the gate
4Register the truckGate ClerkRegisters the truck in the yard spreadsheet and matches it to the ASN in the WMS. This takes 4 to 6 minutes.Excel, Manhattan WMSTruck registered and matched
5Handle a delivery without an ASNClient Account ManagerIf no ASN exists, the Gate Clerk calls the account manager, who confirms with the client whether to accept the delivery. This happens in about 7% of arrivals and takes 20 to 60 minutes.Phone, emailAccept or refuse decision
6Assign a dock doorGate ClerkAssigns a dock door and notifies the Receiving Operator by radio. Trucks wait 20 to 90 minutes for a free door.Excel, radioDock door assigned
7Check seals and damageReceiving OperatorOpens the truck and checks seals and visible damage, taking photos with the handheld. This takes about 5 minutes.Handheld scannerSeal and damage check with photos
8Record visible damageReceiving OperatorIf pallets are visibly damaged, notes the damage on the CMR and calls the Quality Inspector. This applies to about 9% of deliveries.CMR, handheldDamage noted on the CMR
9Unload and scan palletsReceiving OperatorUnloads the pallets and scans each pallet label against the ASN in the WMS. This takes 35 to 50 minutes per truck.Manhattan WMS, scannerScanned pallets
10Count cartonsReceiving OperatorCounts cartons on a sample or in full, depending on the client's rule. This takes 20 to 30 minutes.Manhattan WMS, scannerCarton count
11Flag a discrepancyReceiving OperatorIf the scanned quantity or product code differs from the ASN, flags a discrepancy in the WMS. This happens in about 14% of deliveries.Manhattan WMSDiscrepancy flagged
12Review the discrepancyReceiving SupervisorReviews each discrepancy, recounts if needed and decides to receive as is, receive partially or hold the goods. This takes 15 to 40 minutes.Manhattan WMSReceiving decision
13Report to the clientClient Account ManagerEmails the client with the discrepancy report and waits for instructions. The pallets stay in the receiving area for 2 to 24 hours.EmailClient instructions
14Order a full recountReceiving SupervisorIf the client rejects the recount result, orders a full recount and the operator repeats steps 9 and 10. This rework loop affects about 20% of discrepancies.Manhattan WMSRecount ordered
15Inspect damaged or sampled palletsQuality InspectorInspects damaged or sampled pallets and records accept, quarantine or reject in the WMS. This takes 10 to 20 minutes.Manhattan WMSQuality status per pallet
16Print and apply labelsReceiving OperatorPrints WMS pallet labels with batch and expiry date and applies them. This takes 10 to 15 minutes.Label printer, Manhattan WMSLabelled pallets
17Approve the receiptReceiving SupervisorApproves receipts with differences over 2% of line value, or with any quarantined pallets. About 16% need approval. Other receipts close automatically.Manhattan WMSApproved receipt
18Propose storage locationsManhattan WMS (system)The WMS proposes a storage location for each pallet by product class and slot size. No one keys this step; the proposal appears on the forklift scanner.Manhattan WMSProposed locations
19Put away the palletsForklift DriverPicks up each pallet from the receiving area, scans the pallet and the location label, and places it. This takes 3 to 5 minutes per pallet, after 30 to 120 minutes of waiting in the receiving area.Scanner, forkliftPallets in locations
20Reassign a blocked locationReceiving SupervisorIf the proposed location is full or blocked, the driver calls the supervisor, who reassigns a location manually. This applies to about 6% of pallets.Manhattan WMSNew location assigned
21Release stock and close the entryGate ClerkThe WMS updates stock to available and the client portal shows the new quantity. The Gate Clerk closes the yard entry and returns the signed CMR to the carrier. This takes about 5 minutes.Manhattan WMS, ExcelStock available, CMR returned

7. Decision points and business rules

  • Did the ASN arrive by email? Yes: the Gate Clerk retypes it into the WMS (step 2). About 35% of ASNs.
  • Does an ASN exist for this delivery? No: the Gate Clerk calls the Client Account Manager, who confirms with the client whether to accept it (step 5). About 7% of arrivals.
  • Are pallets visibly damaged? Yes: the operator notes it on the CMR and calls the Quality Inspector (step 8). About 9% of deliveries.
  • Do the scanned quantity or product code match the ASN? No: the operator flags a discrepancy and the Receiving Supervisor decides to receive as is, receive partially or hold (steps 11 and 12). About 14% of deliveries.
  • Does the client reject the recount result? Yes: the supervisor orders a full recount and the operator repeats steps 9 and 10 (step 14). About 20% of discrepancies.
  • Is the difference over 2% of line value, or is any pallet quarantined? Yes: the Receiving Supervisor must approve the receipt. No: it closes automatically (step 17).
  • Is the proposed location full or blocked? Yes: the supervisor reassigns a location manually (step 20). About 6% of pallets.

8. Exceptions

  • Delivery arrives outside the booked time slot (about 20%): trucks queue until a door is free, or are turned away after 3 hours.
  • Mixed pallets with several products (about 5%): the operator breaks them down and relabels, which adds about 30 minutes.
  • Goods without a barcode or with the wrong barcode (about 4%): labels are created manually.
  • Hazardous goods not on the client contract (under 1%): refused.

9. Controls

  • Segregation of duties: the operator who counts goods does not approve receipts with differences.
  • GDP-style traceability for cosmetics: batch and expiry are scanned and stored for every pallet.
  • Damage is recorded on the CMR before the driver leaves, to preserve claims against the carrier.
  • Every WMS transaction records user, time and scanner ID, which gives an audit trail.
  • Monthly cycle counts check stock accuracy.

10. Known issues today

  • Email ASNs have to be retyped, and typing errors create false discrepancies.
  • The yard spreadsheet is edited by two clerks and often shows conflicting information.
  • Clients answer discrepancy emails slowly, so pallets block receiving space for a day or more.
  • Supervisors are called for all discrepancies, even small ones, and become a bottleneck at shift start.
  • Put-away is delayed when drivers move to outbound picking.

11. RACI matrix

R = responsible (does the work), A = accountable (owns the outcome), C = consulted, I = informed.

ActivityGate ClerkOperatorSupervisorQualityForklift DriverAccount Manager
Register the truck and match the ASNA/RIC
Unload, scan and countIA/RI
Record visible damageRAC
Resolve discrepanciesRAC
Inspect damaged or sampled palletsIIA/R
Report discrepancies to the clientCA/R
Approve receipts with differencesIA/RCI
Put away palletsIAR

12. KPIs

Dock-to-stock time
Time from truck arrival at the gate to stock being available in the WMS. Target: under 4 hours.
Receiving accuracy
Share of deliveries received without a discrepancy. Today 86%.
Average truck waiting time
Average minutes between arrival at the gate and a free dock door.
Pallets in the receiving area over 24 hours
Number of pallets still in the receiving area more than 24 hours after being unloaded, counted at the start of each shift.
Email ASN share
Share of advance notices that arrive by email rather than EDI and have to be retyped.

How to adapt this template

  • Replace the company, the WMS and the yard tool with yours. If you have no WMS, name the sheet or the paper form where receipts are recorded.
  • Set your own discrepancy tolerance in step 17. The 2% of line value used here depends on the product value and the client contract.
  • Write down the counting rule per client. Some clients accept a sample count, others require a full count, and that changes unloading time a lot.
  • Add your own special handling: temperature, hazardous goods, serial numbers or quarantine rules, depending on what you store.
  • Check how long pallets really wait in the receiving area. Put-away delays are often caused by staffing between inbound and outbound, not by the process itself.

Questions people ask

What is inbound receiving?

It is the warehouse process of accepting goods from a carrier: checking in the truck, unloading, counting against the expected shipment, inspecting for damage, labelling and recording the stock. It ends when the goods are stored and can be used or shipped.

What is the difference between receiving and put-away?

Receiving is everything that happens until the goods are accepted and labelled in the system. Put-away is the physical move of those pallets to a storage location and the confirmation of that location. Stock is usually only available to the client after both are done.

What is an ASN?

An advance shipping notice is a message from the sender that lists what is on its way: products, quantities, batch numbers and the expected arrival. The warehouse uses it to plan the dock and to check the delivery. When it arrives by email, someone has to enter it into the WMS by hand.

Can I use this template for free?

Yes. Download it in Word or PDF and adapt it to your company. The company in the example is fictional.