Engineering change request and order (ECR and ECO): PDD template and example
This is a complete process definition document (PDD) for engineering change management, also called the ECR and ECO process, engineering change control or product change procedure. It describes how a fictional motor manufacturer raises an engineering change request, assesses its effect on the bill of material, routings, stock and suppliers, decides it at a change board, implements the engineering change order and closes it.
Use it as a starting point. Replace the company details, keep the sections, and walk through each step with the engineers, planners and buyers who actually carry a change through. Most companies change the cost threshold for the board, the list of assessors and the rule for what happens to existing stock. The structure stays the same.
1. Purpose and scope
This procedure describes how Solvik Drives raises, assesses, approves, implements and closes changes to released product data: drawings, bills of material, routings and specifications. It gives engineering, production, purchasing, quality and the warehouse one shared description of who does what, so that a change reaches the shop floor on a known date, with the right stock used up or scrapped, and so that no one builds or buys to an old revision by mistake.
In scope
- Engineering change requests (ECR) for released products, from any department or from a customer
- Impact assessment on the BOM, routing, stock, open orders, suppliers, tooling and documents
- Change board decision
- Engineering change orders (ECO), with revised drawings, BOM and routing
- Effectivity date or serial number and the disposition of old stock
- Supplier and customer notification, and closing the ECO
Out of scope
- New product development before design release
- Changes to process parameters that do not change the released routing
- Tooling construction and supplier qualification
- Quality non-conformances and CAPA
2. Process at a glance
- Trigger
- A person finds a reason to change a released part, assembly, routing or specification.
- Starts when
- The requester raises an ECR in the PLM system.
- Ends when
- The engineering manager closes the ECO after the effectivity date has passed and the old revision is blocked.
- Volume
- About 240 ECRs a year, of which about 170 become an ECO; around 25 are urgent
- Working hours
- Monday to Friday, 07:30 to 16:30. The change board meets on Wednesdays at 10:00.
- Company in this example
- Solvik Drives AS, a manufacturer of electric motors and gearboxes in Trondheim, Norway (about 280 employees, ISO 9001 certified)
- Inputs
- ECR with reason and proposed change, Released drawings, BOM and routing, Stock and open orders, Supplier quotes and lead times, Customer requirements
- Outputs
- Impact assessment, Board decision, ECO with revised drawings, BOM and routing, Effectivity date and stock disposition, Supplier and customer notifications, Closed ECO with evidence
3. Roles and responsibilities
- Requester
- Anyone in engineering, production, purchasing, quality or service who sees the need for a change. Writes the ECR with reason, urgency and proposed solution.
- Design Engineer
- Owns the change technically: screens the ECR, proposes the design solution, prepares revised drawings and BOM, and answers questions from assessors.
- Change Coordinator
- Runs the process in the PLM system: assigns assessments, builds the board pack, records the decision, creates the ECO and tracks open tasks.
- Production Planner
- Assesses the effect on stock, open orders and schedules, and proposes the effectivity date.
- Buyer
- Assesses the effect on suppliers, lead times and open purchase orders, and informs suppliers of the new revision.
- Quality Engineer
- Assesses the effect on inspection plans, certifications and customer requirements, and checks the first article after the change.
- Manufacturing Engineer
- Assesses and updates the routing, work instructions, tooling and fixtures.
- Warehouse Operator
- Blocks, tags, returns or scraps old stock according to the ECO and books the movements.
- Engineering Manager
- Chairs the change board, makes the decision and closes the ECO. The finance manager or the sales director joins when the cost or customer effect is large.
- Supplier (external)
- Receives the change notice, confirms lead time, cost and the date they can supply the new revision.
- Customer (external)
- Approves changes that affect form, fit, function or documentation of a delivered product.
4. Systems
- Siemens Teamcenter: ECR and ECO records, drawings, BOM and revisions
- Microsoft Dynamics 365 Business Central: items, stock, purchase and production orders
- Network drive: routings, work instructions and inspection plans
- Email for supplier and customer notifications
- Excel: list of open ECOs reviewed at the board meeting
5. Process map
Draw your own swimlane: one lane per role from section 3, the steps from section 6 in order, and a diamond for each decision in section 7. Your process will differ from this example, so map it from what your team actually does.
6. Procedure, step by step
| # | Step | Who | What happens | System | Output |
|---|---|---|---|---|---|
| 1 | Raise the ECR | Requester | Describes the problem or opportunity, the affected part numbers, the reason, the urgency and a proposed change. It takes 20 to 40 minutes. | Siemens Teamcenter | Draft ECR |
| 2 | Screen the ECR | Design Engineer | Within 2 working days, checks that the problem is clear and decides whether it is a design change, a documentation fix or not needed. About 15% of ECRs are rejected or returned at this point. | Siemens Teamcenter | Accepted, returned or rejected ECR |
| 3 | Define the proposed solution | Design Engineer | Sketches the solution in CAD, lists the affected assemblies using the where-used report and classifies the change as minor, major or urgent. It takes 2 to 8 hours. | Siemens Teamcenter, CAD | Solution outline and affected item list |
| 4 | Assign impact assessments | Change Coordinator | Creates assessment tasks for planning, purchasing, quality and manufacturing engineering, with a due date of 3 working days (1 day for urgent changes). | Siemens Teamcenter | Assessment tasks open |
| 5 | Assess stock and orders | Production Planner | Reports the stock of the old revision, the quantity on open purchase and production orders, the work in progress and the demand over the next 12 weeks. It takes 30 to 60 minutes. | Business Central | Stock and order impact |
| 6 | Assess supplier impact | Buyer | Checks which suppliers are affected, asks for cost and lead time of the new revision and finds out whether tooling must change. Supplier replies take 2 to 5 days, which is the usual cause of late assessments. | Business Central, email | Supplier impact, cost and lead time |
| 7 | Assess routing and tooling | Manufacturing Engineer | Checks the effect on operations, fixtures, programmes, work instructions and cycle time, and estimates the effort to update them. It takes 1 to 3 hours. | Network drive, Teamcenter | Process impact and effort |
| 8 | Assess quality and compliance | Quality Engineer | Checks inspection plans, product certifications and customer requirements, and decides whether a first article inspection or customer approval is needed. About 20% of changes need customer approval. | Teamcenter, network drive | Quality impact and approval needs |
| 9 | Build the board pack | Change Coordinator | Collects the assessments, adds the total cost of the change (engineering hours, tooling, scrap of old stock) and sends the pack the day before the board. Chases open assessments. It takes about 30 minutes per change. | Siemens Teamcenter, Excel | Board pack |
| 10 | Decide at the change board | Engineering Manager | Approves, rejects or defers the change and sets the effectivity rule and priority. Changes below the cost threshold of 5,000 euros and classed minor can be approved by the manager without the board. About 10% of changes are rejected and 12% are deferred for more information. | Board meeting, Teamcenter | Board decision recorded |
| 11 | Create the ECO | Change Coordinator | Converts the approved ECR into an ECO, assigns the implementation tasks to engineering, manufacturing engineering, planning, purchasing and the warehouse, and sets due dates. | Siemens Teamcenter | ECO with tasks |
| 12 | Revise drawings and BOM | Design Engineer | Prepares the new drawing revision and BOM revision, with the change described in the revision block, and sends them for review and release. It takes 1 to 5 days. | Siemens Teamcenter, CAD | Released drawing and BOM revision |
| 13 | Update routing and instructions | Manufacturing Engineer | Revises the routing, work instructions and tooling to match the new revision and loads the new routing in the ERP, set to start on the effectivity date. | Network drive, Business Central | Updated routing and instructions |
| 14 | Set the effectivity date | Production Planner | Chooses the date or serial number from which the new revision is used. The aim is to use up old stock where it is safe, and the planner changes open production orders and the BOM version in the ERP to match. | Business Central | Effectivity date and updated orders |
| 15 | Notify suppliers and adjust orders | Buyer | Sends the new drawing revision to affected suppliers, changes open purchase orders and records each supplier's confirmation. About 25% of changes need a supplier call because confirmation is not returned within 5 days. | Business Central, email | Supplier confirmations and updated purchase orders |
| 16 | Handle old stock | Warehouse Operator | Blocks, tags, returns to supplier, reworks or scraps the old stock as the ECO says, and books the movements. Stock that reaches the effectivity date unnoticed is the usual way old parts end up in assemblies. | Business Central | Old stock dispositioned |
| 17 | Check the first article | Quality Engineer | Inspects the first parts or the first assembly built to the new revision against the drawing and records the result. If it fails (about 5% of changes), the ECO goes back to the design engineer. | Teamcenter, inspection plan | First article result |
| 18 | Review and close the ECO | Engineering Manager | Checks that all tasks are done, the old revision is blocked in the ERP and the first article passed, then closes the ECO. The coordinator archives the pack with the board decision. | Siemens Teamcenter | Closed ECO |
7. Decision points and business rules
- Is the ECR clear and needed? No: reject or return it to the requester (step 2).
- Is the change minor, major or urgent? Urgent changes get one day for assessments (steps 3 and 4).
- Does the change need customer approval? Yes: the quality engineer arranges it before implementation (step 8).
- Is it below the cost threshold and minor? Yes: the engineering manager may approve without the board (step 10).
- Approve, reject or defer? Deferred changes return with the missing information (step 10).
- From which date or serial number does the new revision apply, and what happens to old stock? (steps 14 and 16).
- Do suppliers confirm the new revision and the date? No: chase and keep the old revision open for them (step 15).
- Does the first article pass? No: return the ECO to the design engineer (step 17).
8. Exceptions
- Urgent change to stop a safety or quality problem (about 10% of ECRs): the engineering manager approves by email, the board is informed afterwards, and the assessments run in 1 day.
- Supplier cannot supply the new revision by the effectivity date (about 15% of changes): the effectivity date is moved or the supplier is asked to keep delivering the old revision for a set quantity.
- Old stock is too large to use up (about 20%): the board decides between rework, return to supplier, scrap and a delayed effectivity date.
- Change requested by a customer: the sales manager attends the board and the quote for the change is agreed before approval.
- Wrong revision found on the shop floor after the effectivity date: production stops the order, quality blocks the parts and the case is recorded as a non-conformance.
9. Controls
- Only released revisions can be used in production orders and purchase orders, and the ERP blocks the old revision after the effectivity date.
- The requester cannot approve their own ECR, and the person who revises the drawing does not release it.
- Every ECO has a record of the assessments, the board decision, the effectivity date and the stock disposition.
- Changes that affect form, fit, function or documentation of a delivered product are not implemented without customer approval.
- The coordinator reviews open ECOs weekly and the board reviews all ECOs older than 30 days.
- Records are kept for the life of the product plus 10 years, in line with customer agreements and ISO 9001 clause 8.5.6.
10. Known issues today
- Supplier impact is assessed by email, so one slow reply holds up the whole board pack.
- Stock and open orders are looked up by hand in the ERP and are out of date by the board meeting.
- Effectivity dates are agreed at the board but not always entered in the ERP, so old and new revisions get mixed.
- Old stock is forgotten after the change, and old parts show up months later.
- The Excel list of open ECOs and the PLM tasks do not match.
11. RACI matrix
R = responsible (does the work), A = accountable (owns the outcome), C = consulted, I = informed.
| Activity | Requester | Design Engineer | Coordinator | Planner / Buyer | Eng. Manager |
|---|---|---|---|---|---|
| Raise and screen the ECR | R | A | I | ||
| Define the solution and affected items | C | A/R | I | ||
| Assess stock, orders and suppliers | C | A | R | ||
| Build the board pack | C | A/R | C | ||
| Decide the change | I | C | R | C | A |
| Revise drawings, BOM and routing | A/R | I | C | ||
| Set effectivity and handle old stock | C | I | A/R | I | |
| Notify suppliers and customers | C | I | A/R | I | |
| Check first article and close the ECO | I | R | R | C | A |
12. KPIs
- ECR to ECO cycle time
- Average calendar days from ECR submission to ECO closure, split by minor, major and urgent.
- Days to decision
- Average calendar days between a complete ECR and the board decision. The target is 10 days.
- Late assessments
- Share of assessment tasks completed after their due date, by function.
- Old revision found after effectivity
- Number of cases a year where an old revision was found in production, in stock or on an order after the effectivity date.
- Cost of obsolete stock from changes
- Value of stock scrapped or reworked because of ECOs, per quarter.
- Open ECOs older than 30 days
- Count of ECOs not closed 30 days after approval. Today about 35.
How to adapt this template
- Replace the company, products and systems with yours. If your PLM and ERP are one system, merge steps 11 to 14 and remove the manual hand-offs.
- Set your own thresholds for who approves without the board. Cost, risk to the customer and number of affected assemblies are the usual criteria.
- Define the effectivity options you use: by date, by serial number, by order or by first use. The choice drives the stock disposition and the supplier notice.
- Check the percentages with real data. The share of ECRs rejected and the time suppliers need to reply show where the process is slow.
- Add customer-specific requirements, such as formal approval periods or a required notification form.
- Walk through the steps with a buyer and a warehouse operator, not only engineers. The old stock and the supplier notice are where the gaps are.
Questions people ask
What is the difference between an ECR and an ECO?
An ECR, or engineering change request, is the proposal: it describes the problem and the change someone wants. An ECO, or engineering change order, is the approved instruction to carry the change out: revised documents, tasks, owners, effectivity date and stock disposition. Some companies use one record with two stages.
What is an effectivity date?
The date, serial number or order from which the new revision must be used. Before it, the old revision stays valid and old stock can be used up. After it, the old revision is blocked. A clear effectivity rule prevents mixed revisions in assemblies.
Who should sit on the change board?
Engineering, production planning, purchasing, quality and manufacturing engineering at a minimum. Add finance or sales when the cost or customer effect is large. Keep the board small enough to decide in an hour, and use an approval route outside the board for minor changes.
What happens to existing stock after a change?
The ECO should say it explicitly: use up, rework, return to supplier or scrap. The choice depends on safety, cost and whether the old and new parts are interchangeable. The warehouse must block or tag the stock so it cannot be picked by accident.
What is the difference between a PDD and an SOP?
An SOP tells one person how to do their part, often screen by screen. A PDD describes the whole process across roles, with decisions, exceptions, controls and volumes, so you can analyse it and change it. Many teams start from the SOP and write the PDD from it.
Can I use this template for free?
Yes. Download it in Word or PDF and adapt it to your company. The company in the example is fictional.